Exhaust ducts replaced and pressure tanks refurbished on Jotun FPSO

For two years, Halvorsen has been installing new exhaust ducts and upgrading pressure vessels on the Jotun FPSO production ship.

Sveinung W. Jensen, Tellus Kommunikasjon

– There are two major tasks. The old exhaust ducts have been replaced with new ones, while in the pressure tanks we have replaced the internals and carried out welding repairs and pressure testing, says project manager Roald Ingebretsen.

The upgrade of the Jotun FPSO at the Worley Rosenberg Stavanger yard is part of Vår Energi's initiative to increase oil recovery from the Balder field in the North Sea.

The work on the exhaust ducts began in March 2022. The ducts in the ship's forward engine room and aft fire pump room are being replaced. Halvorsen are dismantling the old ones, producing new ones in the workshop in Kvinesdal, and installing them on board.

WORKING ON The upgrade of the pressure tanks is also in the final stages. Between 10 and 15 men have been busy with this at the Rosenberg shipyard. In addition, four employees in Kvinesdal are engaged full-time.

Tank bottoms are replaced, tank bottoms are repaired and more nozzles are exchanged.

– We’re breathing new life into 30 offshore tankers. Eight of them have been transported to our workshop in Kvinesdal and renovated here. The rest are being upgraded on the ship itself, says Ingebretsen.

THE STARTING POINT For the assignment, an inspection job with a condition assessment of nearly 50 tanks and 20 heat exchangers was carried out. Faults and deficiencies were identified here, and the customer was informed of what needed to be repaired to extend the lifespan of the equipment.

Halvorsen was given the task of extending the lifespan of the tanks that required upgrading.

Collaborate with us?

We are happy to help you with your project.

Contact us

Talk to us

More projects

Screenshot-2024-12-18-at-15.54.19
New welding robot in place in the workshop
After several months of installation and testing, the robotic welding station is ready for use.
Screenshot-2024-12-03-at-20.11.53-1941x1275-1
Full pipe production in the workshop
Halvorsen is now producing frame structures, pipes and tanks for two major development projects on the Norwegian continental shelf.
AQ9I5024-2268x1275-1
Record-breaking tank produced in the workshop
Never before has a larger tank been produced in Halvorsen's workshop. The 6Mo tank measures almost 20 metres.
Screenshot 2024-09-16 at 16.03.21
The coalescer is leaving the workshop
After several hundred hours of welding and other mechanical work, the coalescer could be transported out of the workshop.
Screenshot-2024-07-01-at-15.08.38-1929x1275-1
Work is in full swing on the coalescer
The 18.5-metre-long coalescer being built in the workshop is taking shape.
AQ9I0822-1913x1275-1
The square tank ready for testing
The first of the six tanks for the new Hugin A platform is nearing completion in the workshop.
AQ9I7561-2048x1365-1
Building large freshwater tank
The first of a total of six topsides for Aker BP's new Hugin A platform in the Yggdrasil area is under construction at the workshop in Øyesletta.
Screenshot-2023-08-14-at-13.44.36
Receives national attention in new video
Through video presentations, Aker BP will showcase its Norwegian subcontractors in the Yggdrasil project. Among the companies being highlighted is Halvorsen.