The heat exchanger is being refurbished

In the workshop, work is underway on extending the lifespan of a 65-tonne heat exchanger.

"This heat exchanger is so powerful that it will never rust. But it must be sealed and withstand pressure for the next 25 years," says Head of Fabrication, John Vester Nielsen.

Intense work is being carried out in the workshop on a flange at one end of the grey colossus. Four men are busy. One is secured with a safety harness and sits on top, communicating with the others.

The heat exchanger is one of several installations that Halvorsen has been commissioned to extend the lifespan of for a customer.

– BEFORE THIS It came here to the workshop, was dismantled from the ship and sent for sandblasting. We reassemble the parts, pressure test and inspect. When our job is finished, the exchanger is sent for painting again before it is handed over to clients, Nielsen explains.

The heat exchanger comprises, among other things, 500 small tubes. These must be sealed and withstand pressure. Through thorough pressure testing of all the tubes, leaks were discovered in eight of them.

– It is impossible to insert new ones. The pipes that are not sealed are therefore plugged. In that way, they are taken out of production and no longer pose a risk, says Nielsen.

BESIDE The heat exchanger has several smaller pressure tanks and filters in a row. They have also been refurbished and are ready for another 25 years in the North Sea.

In the second part of the workshop, the following is carried out: extensive engineering work and upgrade on an eight-metre long, four-metre wide and seven-metre process module. There are over 1000 parts dismantled and reassembled.

Five men are working to secure the flanges.

The bolts are tightened.

John Vester Nielsen, Head of Fabrication, is measuring the diameter of the heat exchanger.

500 small tubes go through the exchanger. Eight of them had to be plugged.

Full concentration on top of the heat exchanger.

Several small pressure vessels and filters have had their service life extended and will be returned to the customer.

Collaborate with us?

We are happy to help you with your project.

Contact us

Talk to us

More projects

Screenshot-2024-12-18-at-15.54.19
New welding robot in place in the workshop
After several months of installation and testing, the robotic welding station is ready for use.
Screenshot-2024-12-03-at-20.11.53-1941x1275-1
Full pipe production in the workshop
Halvorsen is now producing frame structures, pipes and tanks for two major development projects on the Norwegian continental shelf.
AQ9I5024-2268x1275-1
Record-breaking tank produced in the workshop
Never before has a larger tank been produced in Halvorsen's workshop. The 6Mo tank measures almost 20 metres.
Screenshot 2024-09-16 at 16.03.21
The coalescer is leaving the workshop
After several hundred hours of welding and other mechanical work, the coalescer could be transported out of the workshop.
Screenshot-2024-07-01-at-15.08.38-1929x1275-1
Work is in full swing on the coalescer
The 18.5-metre-long coalescer being built in the workshop is taking shape.
AQ9I0822-1913x1275-1
The square tank ready for testing
The first of the six tanks for the new Hugin A platform is nearing completion in the workshop.
20220127_074948-1913x1275-1
Exhaust ducts replaced and pressure tanks refurbished on Jotun FPSO
For two years, Halvorsen has been installing new exhaust ducts and upgrading pressure vessels on the Jotun FPSO production ship.
AQ9I7561-2048x1365-1
Building large freshwater tank
The first of a total of six topsides for Aker BP's new Hugin A platform in the Yggdrasil area is under construction at the workshop in Øyesletta.