Upgrading exhaust pipe to Åsgård B

Here the new parts of one of two identical exhaust pipes are being welded into place. Over 2,000 welding hours are spent on repairs in the project.

– The pipes are to be used on an installation at Åsgård B, but have been stored with us for a while awaiting the start of the project out there, says project manager Stanley Rafoss.

When a construction defect was discovered on a similar job, the Åsgård pipes had to be brought back to the workshop at Øyesletta and upgraded.

– We had to cut the pipes in two and insert a new segment, says Rafoss.

The exhaust pipes have an internal diameter of 2.4 metres and are imposing within the workshop hall.

– Once we've finished the upgrade, the pipes will be transported to the warehouse on site until the customer is ready to receive the entire installation package, says Rafoss.

Halvorsen's client is Aker Solutions, while the end customer is Equinor.

Collaborate with us?

We are happy to help you with your project.

Contact us

Talk to us

More projects

Screenshot-2024-12-18-at-15.54.19
New welding robot in place in the workshop
After several months of installation and testing, the robotic welding station is ready for use.
Screenshot-2024-12-03-at-20.11.53-1941x1275-1
Full pipe production in the workshop
Halvorsen is now producing frame structures, pipes and tanks for two major development projects on the Norwegian continental shelf.
AQ9I5024-2268x1275-1
Record-breaking tank produced in the workshop
Never before has a larger tank been produced in Halvorsen's workshop. The 6Mo tank measures almost 20 metres.
Screenshot 2024-09-16 at 16.03.21
The coalescer is leaving the workshop
After several hundred hours of welding and other mechanical work, the coalescer could be transported out of the workshop.
Screenshot-2024-07-01-at-15.08.38-1929x1275-1
Work is in full swing on the coalescer
The 18.5-metre-long coalescer being built in the workshop is taking shape.
AQ9I0822-1913x1275-1
The square tank ready for testing
The first of the six tanks for the new Hugin A platform is nearing completion in the workshop.
20220127_074948-1913x1275-1
Exhaust ducts replaced and pressure tanks refurbished on Jotun FPSO
For two years, Halvorsen has been installing new exhaust ducts and upgrading pressure vessels on the Jotun FPSO production ship.
AQ9I7561-2048x1365-1
Building large freshwater tank
The first of a total of six topsides for Aker BP's new Hugin A platform in the Yggdrasil area is under construction at the workshop in Øyesletta.